Stories
ACME Solar Boosts Rajasthan's Green Energy with 107 MW BESS Expansion

N
News18•01-10-2026, 17:30
ACME Solar Boosts Rajasthan's Green Energy with 107 MW BESS Expansion
- •ACME Solar Holdings commissioned an additional 107.36 MW / 437.49 MWh BESS capacity across two projects in Rajasthan.
- •The projects were commissioned on September 30, 2026, with Commercial Operation Date (COD) set for October 2, 2026.
- •This expansion brings ACME Solar's total operational Battery Energy Storage System (BESS) capacity to 4.96 GWh.
- •The first phase of the FDRE project, located in Neemri village, Chittorgarh, has a 25-year power purchase agreement with a National REIA.
- •Another project in Kelan village, Bikaner, also has a 25-year power purchase agreement with the National REIA, with full BESS capacity expected within the current financial year.
Key Questions Answered
Following the commissioning of additional BESS capacity across two key projects in Rajasthan, ACME Solar's total operational Battery Energy Storage System capacity now stands at 4.96 GWh.
The Commercial Operation Date for both newly commissioned BESS projects in Rajasthan is scheduled for October 2, 2026.
The new projects are located at Neemri village in Tehsil Rawatbhata (District Chittorgarh) and at Kelan village in Bikaner, Rajasthan.